It’s been a long time since we updated you on progress with the New Scouting Centre, a busy couple of months. As we reported in the April Newsletter the landscaping has been done including a hedge, the walls and ceilings have been fitted and painted, the floors are down in the kitchen and toilets, and most of the plumbing has been done. Continue reading “Almost there …”
1st Northwood Joins District St George’s Parade
The Ruislip Eastcote Northwood Scout District celebrated St George’s Day on Sunday 28th April 2019 at Ruislip Lido. Groups marched on to Willow Lawn from all directions, a good turn out with 1st Northwood well-represented.
There was a fun game as well as the more serious business of presenting awards and renewing of promises. The photos describe the event better than words:
What a Magical Evening
Congratulations to Ian and Ruth Stapleton who organised a fund-raising event with a difference on 27th April. An audience of over 100 was entertained and enthralled by Paul Newton’s magic show at Fairfield church. The event raised a little over £1,000 to add to the New Scouting Centre fund.
1st News Issue #96
To download the latest issue of 1st News just click here.
We’re getting there …
Since New Year, there has been lots of progress:
- Floor has been screeded
- Passmores have finished their work, fitting internal doors etc
- Ceilings have all been fitted by a contractor
- 40% of the 100 or so panels of plasterboard have been fitted by us, at three all-day working parties – it’s got a lot of walls, especially when you have to fit to both sides of the internal partitions!
Imminent works include rainwater drainage and landscaping starting on Friday 1st March; flooring has been ordered and will be fitted to kitchen and toilets week beginning 11th March – we have to finish painting walls and ceilings in those rooms by then. The electricity will be reconnected on 6/7th March. Lots to do!
New Year – New Scouting Centre
Thanks to the large band of volunteers who gave up some of their Christmas break, the new building has insulation fitted in the walls and roof.
The next major milestone will be the floor screed, starting on Monday 7th January. We will have to leave the screed for at least 2 weeks to set before we can walk on it. After that Passmores will return to finish doors, windows and other bits and pieces. Then we can start cladding the walls, installing electrics and plumbing etc – there’s still a great deal to do!
Told You!
We’ve kept saying that the plan showed we would have the roof on the new Scouting Centre by Christmas. Well, guess what? We did it with 3 days to spare! The roofers finished at 9.15 this morning – they made a 7.30am start so they could get an “early go”. Well, it is the shortest day of the year.