Thanks to the large band of volunteers who gave up some of their Christmas break, the new building has insulation fitted in the walls and roof.
The next major milestone will be the floor screed, starting on Monday 7th January. We will have to leave the screed for at least 2 weeks to set before we can walk on it. After that Passmores will return to finish doors, windows and other bits and pieces. Then we can start cladding the walls, installing electrics and plumbing etc – there’s still a great deal to do!